On Tuesday, 18th June, a short press briefing was held on the Otakara Ševčíka road bridge in Brno. The main topic was the transfer of traffic to the newly repaired half of the bridge planned for the night of 20th/21st June. At the same time, works on the other half of the bridge are going to begin.

The reconstruction of the Otakara Ševčíka road bridge in Brno on the I/42 road is being carried out by the JV of OHLA ŽS and Metrostav TBR. After the repaired half of the bridge is opened, the works will move to the other side where the traffic restrictions will be similar to those during the first stage of the works. The traffic on the bridge will again be in the 1+1 mode, with one lane in each direction. Drivers will be directed along clearly marked detour routes which will be different for vehicles of up to 6.5 tonnes and over 6.5 tonnes.
During the works on the first half of the bridge, the completion date was delayed by six months due to the deteriorated condition of the structures compared to the information included in the tender documentation, which the builders found out after the bridge superstructure was uncovered. The entire bridge is scheduled to be operational without traffic restrictions in the summer months of next year.