At the end of July, our subsidiary Tomi – Remont started works on the slab track concreting in the tram tunnel of the large city ring Žabovřeská. The second stage of the construction has thus proceeded to its next phase.

The main works now consist in rectification of the W-tram system rail grid using a system of supports and brackets. This is followed by concreting, where the quality of the surface treatment of the individual dilatation units is paramount. At the same time, the Division Technology employees of OHLA ŽS started works on excavations and concreting the foundations for the traction masts in the areas of both tunnel portals. Furthermore, the trackbed is being excavated to the ground level for the classic tram line at the points where the future slab track will connect to the existing tracks.
The first trams are expected to run there in the first half of the next year.