On Friday, June 9, a ceremonial knocking of the cornerstone, which resembles a chipped piece of wood, took place in front of the premises of Teplárny Brno in Obřanská street. Symbolically, an important project for the Brno energy industry, the preparation of which had taken several years, was started. The construction of the biomass source with the costs of 2.4 billion crowns is being carried out by the JV of the companies OHLA ŽS and ŠKODA PRAHA.

According to the Mayor Markéta Vaňková, the construction of a biomass ‘green source’ will bring two essential benefits to Brno, namely the reduction of the natural gas consumption and the stabilization of heat prices, as well as the improvement of the environment and the reduction of emissions.
The actual construction of the biomass source in the premises in Obřanská street came after the zero stage, when old natural gas boilers and heavy fuel oils boilers were dismantled. In addition, a new pipe connection for the central heat supply between the Líšeň and Lesná districts was built in advance.
The transport of wood chips and the removal of combustion products will be done exclusively by rail in closed containers. For this purpose, the existing railway siding in the premises will be reconstructed. The existing 217.5 m high chimney, which has been a dominant feature of the Obřany district since 1982, will be used for the biomass boiler.
Our colleagues from the division East will carry out the complete construction works in the existing boiler room which will be modified for the new wood chip source, and they will also build a new fuel warehouse with accessories allowing fuel transport to the boiler. Apart from that, the earlier mentioned reconstruction of the existing train siding for transporting wood chips area will be carried out, and new paved areas and further construction objects will be built.
Trial operation of the new source is planned for the autumn of 2024 when the first supplies of ecological heat will be delivered to the central network. The full source operation is expected from the 2025/2026 heating season.