On Thursday, June 8, the reconstruction of the West substation in Olomouc was ceremoniously completed. In terms of ensuring the power supply of the traction line, this is the most important Dopravní podnik města Olomouce (DPMO) building, as it is home to the electrical control room, from where its employees monitor and remotely regulate all of the seven Olomouc substations. The project was carried out by our colleagues from the division Technology from August 2021.

The first step of the reconstruction involved the relocation of the electrical control room as an important part of the Olomouc substation management in order to maintain its smooth operation. Then, a mobile substation was installed which provided power to the traction line during the reconstruction and the technology replacement in the West substation. A trial operation began at the end of 2022, and the final inspection of the building took place in May 2023.
After the completion of the West substation reconstruction, the Olomouc transport company, which was the investor of the project, only has to modernize the Centre substation.
Photo source: DPMO