On Saturday, December 14, the ceremonial completion of the modernisation and electrification of the line from Brno to Zastávka u Brna took place at Zastávka u Brna station. The demanding reconstruction of the 20-kilometre section took two years and was carried out by the JV of Subterra, OHLA ŽS and Elektrizace železnic Praha.

The modernisation of this busy section of regional transport followed the already completed stage from Brno to Střelice, carried out in 2020-2022. The second phase involved the double-tracking and electrification of the line from Střelice to Zastávka u Brna, including the construction of a new Tetčice stop. The Omice and Rosice u Brna stops and the Zastávka u Brna station were also reconstructed.
The reconstruction of this section thus brought the possibility of adding additional regional connections and overall increased comfort for passengers. From Sunday, December 15, the first passengers were able to travel in modern electric train units. The total cost of this construction exceeded 4 billion crowns.