Since this February, the road bridge on Seifertova street in Brno over the railway line Brno – Havlíčkův Brod has been reconstructed. The construction is carried out by the JV of the companies Firesta – Fišer, rekonstrukce, stavby and OHLA ŽS.

The original bridge was built in 1955 and included a structure with a water main. Although it was reconstructed, the works carried out had only a limited lifespan. One of the main defects of the bridge leading to a complete reconstruction was a non-functional insulation which caused a leakage onto the supporting structure and the substructure.
Therefore, the construction works started with a demolition of the load-bearing part up to the bridge caps. The demolition revealed that the structure was in a much worse condition than it was supposed to be. However, the works continued quickly due to the need to meet the key deadline of 1 July for the restart of traffic on the bridge in relation with a diversion of traffic from the closed Husovický tunnel. After the restoration of traffic on the bridge, the construction works will continue until the end of August when the reconstruction of the substructure will be carried out and the pavements and adjacent roads will be repaired.