On Tuesday, November 29, works on electrification of the line between Střelice and Zastávka u Brno, a busy connection with the South Moravian metropolis, ceremoniously started. The second stage of the project follows the already completed section to Střelice and includes, among others, the construction of a second track leading up to Zastávka u Brna. The project, with a total cost of 3.1 billion crowns, is being carried out by the joint venture ZASTŘEL of the companies Subterra, OHLA ŽS and Elektrizace železnic Praha.

The electrification of one of the oldest lines in the Czech Republic is expected to be completed at the end of 2024. Currently, preparatory works have begun, consisting mainly in felling trees and building access roads to the construction site. At the same time, preparation for extraction of the solid material from the track cut has also begun. In the next year, works on bridge structures and the cable distributions relocation and construction will follow up. Works will be carried out on technological buildings, as well as on the dispatch buildings and roadway renovation. Last but not least, water and gas pipelines will be relocated.
As part of the project, the stops in Omice and Rosice u Brna will be reconstructed. A new stop for passengers will be built in Tetčice, with platforms ending at the existing level crossing. A modern signaling equipment, as well as the reconstruction of 8 crossings, will contribute to higher traffic safety. The track speed will increase from the current 80 km/h to up to 120 km/h after the European ETCS safety device installation.