The company OHLA ŽS, in the joint venture with the company VÁHOSTAV – SK, achieved an important milestone this week on the project of the Slovak motorway D1 Hubová–Ivachnová: the boring of the 3,6 km long Čebrať two-tube tunnel. After its completion, the tunnel will be part of an almost fifteen-kilometer-long motorway section, namely the bypass of the town of Ružomberok. This section of the motorway connects Bratislava with Košice and will save motorists more than sixteen minutes.

The Liptov section of the D1 motorway starts at the Hubová interchange, through which it will be connected to the road I/18. The route crosses the Váh river, leads along the northern slope of the Váh valley and the village of Hrboltová. Then, the motorway enters the Čebrať tunnel, exiting it before the Likavka interchange.
The boring of the Čebrať tunnel is carried out using the so-called New Austrian Tunneling Method. This cyclic excavation method involves breaking up the rock, the rock material removal and tunnel securing (reinforcement). As described by Ondřej Tomek, head of this project from the Division Transport Constructions of our company, the exact process of the boring and securing always depends on the type of the rock. Therefore, the excavation speed changed during the construction depending on the conditions given by the geological characteristics of the rock. An interesting fact is the discovery of a cave during the construction of the tunnel.