On Tuesday, May 31, the second stage of concreting the supporting structure of the bridge over the Dřevnice river in Zlín took place. This completely new bridge will connect the Zlín-East industrial zone with the existing I/49 road. The construction of selected bridge parts is carried out by the Center Bridges of OHLA ŽS for the joint venture “Connection of PZ Zlín STRABAG + KKS”. The investor of the construction with a total cost of 63 million crowns is the Statutory City of Zlín.

The bridge runs across a single-track railway line and the Dřevnice river. The substructure consists of end supports with bridge caps and six middle supports and the load-bearing structure is constructed as a monolithic prestressed continuous beam.
During the concreting in the first and second stages, almost 900 m3 of fresh concrete was placed. In the following days, the support formwork will be assembled and concrete beams will be reinforced for the third and the most substantial stage, which represents spanning the river, the track and a cycle path. During this stage, approximately 850 m3 of fresh concrete will be placed.
The bridge is expected to be completed this October.