On Monday, 24th June, the University Hospital Ostrava held a grand opening of the Inpatient wards block which took two years to reconstruct and cost 483 million crowns. The building, which this year celebrates 30 years since its completion, has received new air conditioning, an insulated facade and roof and completely replaced windows.

The pavilion L belongs to the tallest buildings of the hospital complex in Ostrava, it has 12 above-ground and 2 underground floors. The main objective of the construction works, which were carried out on the exterior of the building by the JV of the companies OHLA ŽS and BDSTAV MORAVA, was to reduce the energy consumption of the building.
This part of the repairs cost 224 million crowns and included the insulation of the roof, the facade of the entire building and the replacement of more than 500 windows. The largest intervention in the appearance of the building was the removal of 340 balconies. Each of them weighed around 4 tonnes and had to be cut away with special diamond discs with a diameter of 1.2 metres.