Since the very beginning, the construction of the Ružomberok bypass, one of the Slovak motorway D1 Hubová–Ivachnová section, was burdened with complications brought about by unpredictable geological conditions. For example, they made the construction in the originally intended route completely impossible in the section of the Čebrať tunnel, and in other places required the adoption of additional technical measures. It was also necessary to consider the requirements of the new Slovak legislation in order to put into operation a truly modern work. Dealing with these issues was not easy both from the technical and the contractual point of view and took longer than we had anticipated.

The contractor the Čebrať Joint Venture, consisting of the companies OHLA ŽS and VÁHOSTAV – SK, long sought an agreement with the client, the Slovak National Highway Company (Národná diaľničná spoločnosť, NDS, a.s.) and made every effort to ensure that the D1 Hubová–Ivachnová construction continued and it was not necessary to significantly postpone the opening date of the motorway.
In mid-July 2022, all interested parties managed to create prerequisites for the interim financing of the construction until the final agreement on the commercial and time conditions for the entire project has been signed. The first step towards the completion of this important infrastructure construction in Slovakia has thus been taken. In this context, it is essential to appreciate the effort of dozens of experts on both the client’s and the contractor’s side, who participated in preparing the detailed documents necessary to create the aforementioned prerequisites.
“This year, a symbolic milestone, the digging of the Čebrať tunnel, will be reached and works will continue on the secondary lining so that in 2023 the tunnel is ready for the installation of the technological equipment. Most of the bridge structures will be largely completed in 2022, and works will also continue on additional stability measures. These are structures that ensure the stability of the slope and of the motorway body in locations with new unpredictable landslides. Due to very complex geological conditions, a technically demanding and unique solution has been proposed at 12.0-12.3 kilometers. At the same time, works will continue on the realization of the motorway route, with the structural layers of the pavement already being laid in some sections.” says Ing. Ondřej Tomek, construction director from the Division Transport Construction of OHLA ŽS, a.s.