On Wednesday, October 7, construction of the new Libuš–Nové Dvory tram line began with a ceremonial laying of the cornerstone.

The new 1.8-kilometer double-track line will connect to the section that opened in 2023 and will end in a block loop. It will significantly improve transportation access to the planned city district and provide direct connections to the future Metro Line D.
The project is being carried out by our colleagues from the West Division. For the contractor, this marks a return to a familiar site, where OHLA ŽS successfully completed the previous phase of the Modřany–Libuš Housing Estate. The project itself consists of a total of 78 buildings and utility structures. Roughly half of the construction time will be taken up by demanding earthwork and the relocation of nearly two kilometers of DN 1200 water supply lines from the Želivka reservoir, which will free up space on Novodvorská Street for the track itself and the future Libuš Metro Line D station.
During the second construction season, work will continue with the laying of the track itself, which will be covered with grass on Novodvorská Street. The contract also includes the construction of the foundations for a barrier-free underpass leading to the southern metro concourse in Libuš and the connection to the terminal station on Durychova Street. Trial operations for passengers are scheduled to begin at the end of 2028.