As part of the inspection day, the Minister of Transport Martin Kupka together with the Správa železnic CEO Jiří Svoboda visited the construction site of one of the most important projects on the Czech railways.

The modernization of the line between Praha and Kladno with a branch to the Václav Havel Airport will bring a faster connection between the capital and the largest city in the Central Bohemia Region. At the same time, it will significantly contribute to an easier access to the Václav Havel Airport. The construction costing almost three billion crowns was ceremonially launched at the beginning of this year, and OHLA ŽS is carrying it out in a JV.
The entire project is divided into ten constructions. On the Praha side, the first modernization steps consisted in preparatory works. In the Stromovka nature reserve, the historic wall had to be relocated, and the railway embankment was removed between Strojnická and U Výstaviště streets. In the spring, a temporary track was put into operation to maintain train traffic in the direction of Kralupy nad Vltavou, and a bridge for pedestrians and cyclists was installed, connecting Veletržní and Dělnická streets.
Currently, works are being done simultaneously on the sections Kladno – Kladno-Ostrovec and Praha-Bubny – Praha-Výstaviště. The main project goal is the modernization of the Praha-Bubny station, the double-tracking of the approximately 1.3-kilometer line, its electrification and the construction of a completely new Praha-Výstaviště stop. The volume of works is the largest here, approximately 2,000 m3 of soil is extracted every day.
As the Minister Kupka stated: “At both sites, it can be seen that the builders have already done a great deal of works. The railway, which until now was a living reminder of the former Buštěhrad railway, is now beginning to take on a form corresponding to the 21st century.”
The first works in Kladno started at the end of last year. A section of the track is currently being rebuilt, where an underpass and an island platform are being built. Furthermore, a new track underpass in Walkerova street is being prepared. At the same time, frame walls are being built in Sportovců and Klikorova streets. In Kladno-Ostrovec, the hot water piping is being relocated.
In the coming months, the main works should move on to the Praha-Ruzyně – Praha Václav Havel Airport section.