The extensive reconstruction of the Šance water reservoir in the Moravian-Silesian Region lasted in the period of 2015-2018. Since the construction of the dam in 1969, it was the first such a large and extensive reconstruction. The main purpose of the reconstruction was to strengthen the flood protection, better water flow regulation and efficient drinking water supply and, above all, to improve the overall operational safety.
Preparations for reconstruction lasted almost ten years. When it was built fifty years ago, there were less demanding capacity and operation requirements for such a large reservoir which now has to contain up to ten-thousand-year water. Most of the work was therefore concentrated in the vicinity of the dam and measures were in place to help with such extreme floods.
The builders have increased the crest dam, generally reinforced the dam with the limestone from the nearby landslip which also endangered the dam´s safety, have built a storage addit but, after all, they have raised the spillway, extended twice the slipping capacity, the so called “plunge pool”, i.e. the place where the water flows out of the reservoir into the riverbed.
The modernization also affected the water management system and the system for measuring, observing and collecting water management data which are sent by remote transmission to the central dispatching center in Ostrava. The technical facilities are located in the newly built operating center where an information center will be created in the future. The dam of the water reservoir is part of a hiking trail, so it is counted with the interest of the passers-by.
| Basic information | |
|---|---|
| Amount | 438 million CZK |
| Commencement date | 2015 |
| Completion date | 2018 |
| Investor | Povodí Odry |
| Designer | Aquatis |
| Contractors | OHL ŽS |