The project consisted in the reconstruction of the Beroun railway station (the complete passenger station and a part of the classification yard) and the reconstruction of a part of the connecting line section to the Králův Dvůr stop (included). The project is part of the third transit corridor (Praha–Plzeň–Cheb), and the total length is 5.135 km.

The railway line optimization consisted in: increasing the line speed to up to 160 km/h, the modernization of the signaling equipment, the introduction of permissible axle pressure of 22.5 tons, the class D4 load capacity, as well as the provision of the spatial throughput for the UIC–GC load gauge. In addition to greater safety, the optimization has brought passengers a better travel comfort, a reduction in the travel time and more attractive rail transportation in a very popular tourist location.

The reconstructed parts included the railway superstructure and substructure (aprox. 22.3 km of rails, 76 new switches), as well as platform modification (2 island and 3 external platforms) including wheelchair access for passengers. Crossings, underpasses, bridges and culverts were reconstructed. A new underpass was built and the signaling system was modernized with possible future connection to the Central Dispatch Center Praha. Communication and information systems were installed, and the track metallic and optical cables and local cabling were laid. The traction line was reconstructed, including the dispatching control technology, as the two-track line is electrified partly with a 3 kV DC current system and partly with a 25 kV AC current system. Electronic protection of technological objects and technologies was provided, a CCTV system to ensure passenger safety was installed and the anti-noise measures were introduced.

Basic information
Amount 2,1 billion CZK
Commencement date 2016
Completion date 2022
Investor Správa železnic
Designer METROPROJEKT Praha a.s.
Contractors In joint venture