The project consisted in the complete reconstruction and modernization of the Horní Cerekev traction power station.
The new transformer points are located at the same place as the original ones. They are roofed, their shell is a reinforced concrete wall system placed on reinforced concrete beams, and they have two traction transformers installed.
In the Horní Cerekev traction power station, two new filter compensation devices are installed; they are supposed to cooperate with one traction transformer.
The 25 kV substation has undergone the biggest changes. The original outdoor substation design was replaced by an indoor one. The new 25 kV substation is designed as internal cabinet, placed in a new prefabricated concrete building. This guarantees a better device protection and its longer service life. The 25kV switchboard itself is a production of the OHLA ŽS company, Division Technologies, and is designed as a metal-covered, air-insulated switchboard with a retractable switch, which consists of sixteen fields, in two rows opposite each other.
| Basic information | |
|---|---|
| Amount | 186 million CZK |
| Commencement date | 2018 |
| Completion date | 2020 |
| Investor | Správa železnic |
| Designer | SUDOP Brno, spol. s.r.o. |
| Contractors | In joint venture |