The project’s objective was to reconstruct the double-track electrified national railway line in the section Dětmarovice – Petrovice u Karviné – the state border of the Czech Republic/PL in the Moravian-Silesian Region. The main objective was to eliminate speed drops, ensure interoperability and increase the reliability, safety and comfort of railway operations, including barrier-free access for people with reduced mobility and orientation. The maximum line speed was increased up to 140 km/h and the total length of the construction was 9.625 km.

The project encompassed the reconstruction of the railway superstructure and substructure in a total length of 25.5 km, including 41 new switches in stations and branches, island and side platforms, six level crossings with all-rubber construction, and 16 bridge structures. Furthermore, 834 m of cable infrastructure, utilities, roads and paved areas were built.

The overhead line of the 3 kV DC system, adapted for a speed of 140 km/h, was also reconstructed, including derailing and power technology (two traction substations, LV substation, electric switch heating at 67 switches, remote control and monitoring equipment, and the relocation of power distribution lines, earthing and lighting of stations and stops).

In both stations, as well as in the Závada stop, new communication equipment (cabling, transmission system, electrical safety signalling, information and radio systems, camera system) was installed.

Following completion of the construction work, the European Rail Traffic Management System (ERTMS) and the European Train Control System (ETCS) were deployed and tested throughout the reconstructed section.

Basic information
Amount 3 billion CZK without VAT
Commencement date 2020
Completion date 2024
Investor Správa železnic
Contractors in join venture