In autumn 2021, a major reconstruction of the railway line between Brno and Blansko began. This line is of national importance and is part of the 1st transit corridor leading from Děčín through Praha to Břeclav. As the first of three reconstructed sections, construction works began on the project “Adamov–Blansko, BC”.
The project is located in the South Moravian region, in the Adamov–Blansko line section which is part of the national double-track corridor railway line no. 260 Brno – Česká Třebová. The subject was the reconstruction of the interstation section Adamov (excluded) – Blansko (excluded) including the Adamov-zastávka (a stop). The total length of the construction is 7.05 km. By reconstructing the track, speed drops were removed; safety as well as traffic flow were increased, and a wheelchair access to the platform was built. At the same time, interoperability parameters were ensured, and requirements of the applicable legislation were met.
The railway superstructure (60E2 on concrete sleepers) and the subgrade under both tracks were reconstructed. In the Adamov-zastávka stop, a new island platform (170 m long) was built with the platform edge height of 550 mm above the track. In total, 9 bridges including a new underpass to the platform, 9 culverts and 18 supporting or frame walls, roads, as well as a cable duct at the Adamov-zastávka stop and distribution networks were reconstructed or newly built. About 20,000 m2 of rocky slopes were rehabilitated using anchored steel nets. All five tunnels were reconstructed. Four of them (3 double-track and 1 single-track) were rehabilitated, while the single-track tunnel under Nový hrad with a length of 557 m was completely rebuilt. The existing lining was demolished, and a new primary lining made of sprayed concrete, insulation and the secondary lining made of a reinforced concrete monolith were built. In addition, the signalling installation (3rd category), the telecommunication plant, the high-current equipment and traction lines of the AC traction system 25 kV 50 Hz including the earthing connection with rails were reconstructed.
The reconstruction was done during a complete one-year traffic closure (the so-called non-railway operation) of both tracks while substitute bus services were introduced. During this traffic closure, the Adamov railway station and the interstation section Brno-Maloměřice – Adamov were reconstructed.
| Basic information | |
|---|---|
| Amount | 2.726 billion CZK |
| Commencement date | 2021 |
| Completion date | 2023 |
| Investor | Správa železnic |
| Designer | SUDOP Brno, PRODEX |
| Contractors | In joint venture |