Construction of the grade-separated interchange of the D1 and D2 motorways is continuing according to the established schedule. The demolition of a bridge on the D1 motorway was planned for the past weekend, which required the complete closure of the D2 motorway for a certain period, as the bridge crossed above it. Despite freezing weather conditions, the demolition was successfully completed, and partial traffic returned to the D2 on Sunday.

The affected section of the motorway was completely closed from Friday evening until Sunday afternoon, with the main demolition work taking place from Saturday evening to Sunday morning. On Friday, after the restrictions came into effect, safety barriers were dismantled and other initial preparations for removing the bridge were carried out.
The actual demolition began on Saturday at 6:00 p.m. and lasted a total of 16 hours. Working through the night under floodlights, in temperatures dropping to around -8 degrees Celsius and during light snowfall, machinery gradually dismantled the bridge structure, which was completely gone by early Sunday morning. Due to the frost, the demolition equipment required frequent servicing, but the team was prepared for this as well and the work proceeded according to plan. The material was continuously crushed and transported away for disposal.
All work was completed and the site cleared by around 10:00 a.m. After the reinstallation of steel and concrete safety barriers, traffic on the D2 motorway gradually resumed under the same conditions that were in place before the weekend closure.
Police were also present on site throughout the night, ensuring the safety of surrounding traffic and directing vehicles via the operational ramp on the Bratislava–Ostrava route.