After twenty-two months of work, the construction of the wastewater sewer system in Penčice, a local part of Přerov, has been completed. The project, costing nearly 100 million CZK, was funded by the city of Přerov and the company Vodovody a kanalizace Přerov, with roughly half of the costs covered by a grant from the Operational Programme Environment 2021–2027.

The Eastern division carried out the sewer reconstruction. In just under two years, nearly 5.5 kilometres of new sewer lines were installed. The gravity sewer section, made of plastic pipes, measures just under three kilometres; the remaining section is a pressure sewer, and four wastewater pumping stations were added. The wastewater will then be treated at the wastewater treatment plant in Čekyně, a neighbouring area. The project also included the relocation of utility networks and new electrical cable connections.
This project, which the residents of Penčice had been waiting for decades, will improve the local environment, the quality of surface water, and the residents’ quality of life. Approximately 150 requests for household sewer connections were received.
The construction was officially completed at the end of June, ahead of schedule. Originally, it was planned to take seven months longer, with completion expected in spring 2026. A comprehensive road repair by a different contractor will follow this sewer reconstruction in the village.