Since June of this year, our colleagues from the area Central Bohemia, the division West, have been working on a project called “Construction activities COMPASS-Upgrade – 2nd stage”. A completely new tokamak COMPASS Upgrade with world-unique parameters will be built on the site of the successful Czech tokamak. During the second stage, two service halls for electrical equipment and two impulse generators will be built, as well as campus roads and the surroundings of the halls.

The larger of the two halls, which will be used for electrical equipment, is built as a classic monolithic structure walled with Ytong blocks. The entire structure will be closed with aluminum fillings in the Alucobond grid facade, and the internal layout will be made up from a combination of plasterboard walls and Ytong partitions.
A highly sophisticated part of this stage are the foundations for two flywheel generators in the second hall. These foundations are placed on a suspension due to the “excitation forces” of the generators and are made of a concrete block weighing approximately 1,000 tons (more than 400 m3 of concrete and 60 tons of reinforcement). All of this is stored on 12 support blocks protruding from the base slab. The foundation itself is placed 1.6 meters above the base slab and “floats” on spring bushings.
Another fact worth noting will be the installation of these large generators in the Prague wider center. As the generator’s heaviest part weighs around 60 tons, a large mobile crane or a gantry crane in the form of a mobile structure will be necessary for the installation. This would have no comparison in Prague.
This project, which is expected to be completed in autumn next year, is full of unusual and non-standard solutions. Therefore, it requires high expertise and precision on the part of the entire realization team of the division West.
Visualization source: DES Praha