A brand-new, modern service centre for RegioPanter regional trains has been under construction for nearly a year at the Czech Railways depot in Olomouc. The new hall will replace the existing inadequate facilities. The reconstruction, valued at over CZK 400 million and carried out by the Eastern Division production team, is progressing according to schedule and is expected to be completed this autumn.

The full reconstruction of Hall B began last March. Since then, all planned demolitions have been completed, the original building envelope has been removed, and work on the extension of the hall is ongoing. The old steel structural elements have also been dismantled and replaced with new ones. Foundations for the extension have been completed. Currently, installation of the new building envelope is underway, along with continued construction of the extension.
The main utility networks for sewerage, water supply and the retention tank have also been completed; they now only need to be connected to the building and fitted with the required technology. Roof installation will follow, after which work will move to the interior of the hall. Inside, masonry works, installation of metal components and preparation of all main systems—such as HVAC, heating and electrical installations—will take place.
The reconstruction is technically demanding, as it is being carried out under full operation of the maintenance facility. Therefore, coordination of all trades, careful planning of individual phases and a strong emphasis on occupational safety are more important than ever.
The modernisation of maintenance facilities goes hand in hand with the renewal of the rolling stock. RegioPanter train units could not fit into the original hall, which is why it will be extended from 85 to 123 metres and equipped with modern technology meeting current requirements. The hall will be insulated, heated, fitted with an overhead crane for easier access, as well as diagnostic and other technical equipment. The facilities will also provide greater comfort and safety for maintenance staff.